LaGrange
church of christ – home page and index
Note – For scanned document
copies related to land and building projects, see the financial
Records page
Land and Building
In September 1954, the congregation purchased land from Noel
and Georgia Rowan. The land began to be
leveled on April 7, 1955. The building roof was completed on December 31, 1955. Interior work began on April 13, 1956, and the congregation
met in the building for the first time on September 23, 1956. Dedication Sunday was declared for September
30th, and advertised with the Charles Coil Gospel Meeting in the
LaGrange Standard newspaper.
On October
14, 1957, the congregation borrowed $4,000 to construct a
preacher’s house. Contributions toward
the preacher’s house were received from several other congregations and members
around the U.S. The preacher’s house was completed in the
spring of 1958, and Paul Hosse’s family was the first
to occupy it that year.
In September 1959, the men decided to cement the ground
under the preacher’s house carport and construct a shop (“the shed”) at the
east end of the auditorium. On November 4, 1959, the men
decided to borrow $200 to complete the two projects.
In November 1962, the congregation completed the auditorium,
with painted plaster on the brick walls and ceiling, and tile on the cement
floor. The painting was done on New
Year’s Day, January 1, 1963. The floor tile was installed on January 2nd. The chairs were reset on January 5th.
On April
6, 1964, the men decided to make and mount “CHURCH OF CHRIST”
letters on the west side (Townline
Road side) of the church building. The letters were mounted on May 8th.
On August
3, 1964, the men decided to install sidewalks at the church
building. They were finished August 22nd.
In October 1964, the men installed a partition in the back
of the auditorium for a classroom.
On December
17, 1964, the congregation placed an order with Endicott for pews
to replace their auditorium chairs. The
pews were installed by Endicott on February 6, 1965.
On January
6, 1965, the congregation ordered a fixed pulpit stand and
communion table from Middlebury Church Furniture Company.
In May 1967, curb stops were added to the parking lot.
In October 1968, the congregation put new shingles on the
church building roof.
Starting March 1969, the congregation remodeled and
installed carpeting in the preacher’s house.
The project was finished on June 25th.
On September
7, 1969, the men decided to build four new classrooms to the west
of the existing building. The large
classroom at the back of the auditorium was to be converted into a nursery with
a window into the auditorium. An
additional 20’
of land south of the church building was purchased from Georgia Rowan for
$200. On October 28th the
project started with tearing out the porch, to turn it the other
direction. As part of the project, the
partition was removed in the rest room, making one large ladies’ rest room. The men’s rest room was included in the new
wing. On February 4th, carpet
was laid in the new addition, with enough left over for a runner in the
auditorium. The North Central
congregation in Indianapolis
provided most of the tables and chairs.
Other furnishings, painting, and exterior brickwork were completed
throughout 1970.
On April
7, 1971, the men decided to purchase Georgia Rowan’s remaining lot
on the northeast corner of the intersection of Church Street and Townline Road, at a cost of $1,000.
In July 1971, the men decided to finish the parking lot with
limestone.
On July
23, 1972, the men decided to add two bedrooms and another bathroom
at the west end of the preacher’s house.
The addition was completed in time for Norm and Merilyn Herron’s family,
with their five children, to occupy on August 29th.
On September
12, 1976, the men decided to proceed with a new classroom addition
south of the auditorium. The addition
nearly doubled the square footage of the building. It was first used by the teens on January 16, 1977. The teens, hosting the first LaGrange Youth
Rally, used the unfinished lobby, aisle and fellowship room for their worship
service and potluck lunch. The carpet
installation began on April 6th.
On April 22nd, the baseboards and molding were
completed. The classroom addition began
regular use on April 24,
1977.
On November
26, 1978, the men decided to purchase Fay’s Pizza property on the
southeast corner of the intersection of Central Avenue (US-20) and Townline Road, at a
cost of $30,000. The purchase completed
the congregation’s land expansion for the entire block along Townline Road, and increased the exposure
of the building to the heavy traffic on US-20.